The screw factory from the Commission's guidance, calculated by this tool. Load it with one click
and every figure below appears in step 4 — the example is public, so nothing is hidden.
Communication Template (.xlsx)
The Commission's official workbook (v2.1) with your figures in the input sheets — A_InstData,
B_EmInst, D_Processes and E_PurchPrec. Its formulas are left untouched, so it recalculates in Excel.
Buyer report (PDF)
One page for your EU importer: your value, the default it replaces, and the estimated saving on
their CBAM certificates — with the sources and the carbon price date printed next to every figure.
Common questions
Is a non-EU producer legally required to report CBAM data?
No — the legal obligation sits with the EU importer, but without your data the importer must use a default value with a penalty mark-up, so most customers will insist on receiving it.
In practice the request arrives as a commercial condition: send actual emissions data or share the extra cost of the default value.
Source: Regulation (EU) 2023/956, Articles 4 and 6
How is the CBAM emissions value per tonne calculated?
It is your installation's direct emissions attributed to the product, plus the emissions embedded in the CBAM materials you bought and consumed, divided by the tonnes of product you made.
The result is tonnes of CO₂e per tonne of goods for one calendar year. Scrap and returned product are excluded from output; offcuts and losses stay on the input side.
Source: Regulation (EU) 2023/956, Annex IV
Do electricity emissions count for steel and aluminium under CBAM?
No — in the definitive period only direct emissions count for iron, steel and aluminium; electricity is reported in the template but does not enter the product's value, with sintered ore as the single exception.
Electric arc furnace producers still count electrodes, natural gas and the carbon in scrap and alloys.
Source: Regulation (EU) 2023/956, Annex II; Commission Guidance No. 5d/5e, pp. 8–9
Does my CBAM data need to be verified?
Yes — from 2026 actual emission values can only be used by the importer once they have been verified by an accredited verifier; until then, describe your figures as verification-ready, not verified.
A first calculated file is still useful: it shows your customer the likely saving and is the input the verifier checks.
Source: Regulation (EU) 2023/956, Article 8; Commission Guidance No. 3, p. 50
Does CBAM File send my production data anywhere?
No — every calculation and the filled template are produced inside your browser; your production, fuel and purchase figures are never uploaded to our servers.
The only thing we ever store is an email address, and only if you ask for regulatory update alerts.
Source: CBAM File Privacy Policy